In September, construction works continued on schedule:
Block I: The lower slab of the 4th commercial floor is under construction. The monolithic reinforced concrete frame for two underground parking levels and three commercial floors has been completed.
Block II: The lower slab of the 2nd floor has been completed. At this stage, construction of two underground parking levels and one commercial floor has been finalized.
The project is progressing steadily according to plan.